Friends of Irish Environment bring High Court challenge against Shannon LNG planning permission
An Bord Pleanála granted planning permission in March 2025 for a 600-megawatt power plant and energy storage facility on a 255-hectare site between Tarbert and Ballylongford on the Shannon estuary in north Co Kerry. Friends of the Irish Environment brought a High Court judicial review challenge, arguing the decision contravenes the Kerry County Development Plan 2022-2028 and the Listowel Municipal District Local Area Plan 2020-2026. On 12 May 2025, Mr Justice Richard Humphreys granted permission to bring proceedings against ABP, Ireland, the Attorney General and the Minister for Housing, with Shannon LNG as a notice party. The case is set to return to court in two weeks.
- Reportednot reported
- Arrestednot reported
- Chargednot reported
- In court12 May
- Verdict
- Sentenced
Key facts
consolidated from all reports- What happened
- ABP granted planning permission in March 2025 for a 600-megawatt power plant and energy storage facility on a 255-hectare site.
- Friends of the Irish Environment argue the decision constitutes a material contravention of the Kerry County Development Plan 2022-2028 and the Listowel Municipal District Local Area Plan 2020-2026.
- The proposed development will account for one third of all budgeted emissions from the electricity sector in 2030.
- Where
- The proposed site is between Tarbert and Ballylongford on the Shannon estuary in north Co Kerry.
- In court
- On 12 May 2025, Mr Justice Richard Humphreys granted permission to bring judicial review proceedings against ABP, Ireland, the Attorney General and the Minister for Housing.
- Shannon LNG is a notice party in the action.
- The case is set to return to court in two weeks.
- Other details
- In September 2024, Mr Justice Humphreys overturned the board's refusal of planning permission for the power plant, battery energy storage system and regasification unit at the Shannon estuary site.
7 statements extracted from the articles
- whatABP granted permission in March for a 600-megawatt power plant and energy storage facility on a 255-hectare site. (irishtimes.com)
- whatThe proposed development will account for one third of all budgeted emissions from the electricity sector in 2030. (irishtimes.com)
- whatFIE says the decision constitutes a material contravention of the Kerry County Development Plan 2022-2028 and Listowel Municipal District Local Area Plan 2020-2026. (irishtimes.com)
- whereThe proposed site is between Tarbert and Ballylongford on the Shannon estuary. (irishtimes.com)
- courtMr Justice Richard Humphreys gave permission to bring judicial review proceedings against ABP, Ireland, the Attorney General and the Minister for Housing. (irishtimes.com)
- courtShannon LNG is a notice party in the action. (irishtimes.com)
- courtThe case returns to court in two weeks. (irishtimes.com)
The reporting
newest first- 12 May2025Friends of Irish Environment bring High Court challenge against Shannon LNG permission
First report of the FIE judicial review; Mr Justice Humphreys granted permission to bring proceedings on 12 May 2025, with the case returning to court in two weeks.